66,99 €
CODE OF PRACTICE FOR PROGRAMME MANAGEMENT IN THE BUILT ENVIRONMENT Manage a construction programme from start to finish with this up-to-date guide The maturation and proliferation of project management principles has been one of the most important stories in recent business history. So widely has project management spread throughout the corporate world that it has now given way to a similar discipline, programme management, designed to align, coordinate and manage a number of related projects as a whole. In the construction industry particularly, programme management can deliver benefits that would not have been possible to realise had individual projects been managed independently. Produced by the Chartered Institute of Building (CIOB), the revised Code of Practice for Programme Management in the Built Environment provides a comprehensive overview of the tools required to deliver such benefits, and how they are applied in construction programmes. A natural complement to the CIOB's popular Code of Practice for Project Management for the Built Environment, it is now fully updated to reflect new insights and best practices. Readers of the second edition of Code of Practice for Programme Management in the Built Environment will find: * Theoretical and practical insights derived from research and experience * Coverage of setting up programmes successfully so that teams feel confident to deliver the final outcome * Guidelines for implementing programme management for the built environment Code of Practice for Programme Management in the Built Environment is ideal for programme management and project management professionals involved in this industry and in particular, contractors and client organisations, as well as for advanced undergraduate and postgraduate students in construction project management and other related disciplines. The Chartered Institute of Building is the world's largest professional body for construction management and leadership. It has a Royal Charter to promote the science and practice of building and construction for the benefit of society. Members across the world work in the development, conservation, and improvement of the built environment.
Sie lesen das E-Book in den Legimi-Apps auf:
Seitenzahl: 238
Veröffentlichungsjahr: 2024
Cover
Table of Contents
Title Page
Copyright
Foreword
Acknowledgements
List of Figures
Working Group (WG) of the Code of Practice for Programme Management
Glossary
1 Programme Management in Context
1.1 Introduction
1.2 Applying programme management in practice
1.3 Programme organisation
Notes
2 Stage A: Inception
2.1 Purpose of this stage
2.2 Key activities of this stage
2.3 Key roles and responsibilities of this stage
3 Stage B: Initiation
3.1 Purpose of this stage
3.2 Key activities of this stage
3.3 Key roles and responsibilities of this stage
4 Stage C: Definition
4.1 Purpose of this stage
4.2 Key activities at this stage
4.3 Key roles and responsibilities of this stage
Note
5 Stage D: Implementation
5.1 Purpose of this stage
5.2 Key activities of this stage
5.3 Key roles and responsibilities of this stage
6 Stage E: Benefits Realisation and Transition
6.1 Purpose of this stage
6.2 Key activities of this stage
6.3 Key roles and responsibilities of this stage
7 Stage F: Closure
7.1 Purpose of this stage
7.2 Key activities of this stage
7.3 Key roles and responsibilities of this stage
Appendix A: Programme Delivery Matrix
A.1 Background
A.2 Use of the Programme Delivery Matrix
Note
Appendix B: Tools and Techniques
B.1 Background
Appendix C: Templates
C.1 Vision statement
C.2 High‐level programme scope
C.3 Programme mandate
C.4 Programme brief
C.5 Business case
C.6 Monthly programme report
C.7 Programme highlight report
C.8 Benefits profile
C.9 Tracking benefits: benefits‐monitoring
C.10 Programme closure report
Note
Appendix D: Key Roles: Skills and Competencies
D.1 Programme manager
D.2 Programme business change manager
D.3 Programme benefits realisation manager
D.4 Programme financial manager
D.5 Head of programme management office
D.6 Programme risk manager
D.7 Programme scheduling manager
D.8 Programme cost manager
Bibliography
Past Working Group of the
Code of Practice for Programme Management
Index
End User License Agreement
Chapter 1
Figure 1.1 Programme Delivery Triangle.
Figure 1.2 Organisational interfaces in the programme context. Adapted from ...
Figure 1.3 Six themes for programme management in the built environment.
Figure 1.4 Programme, projects and benefits.
Figure 1.5 CIOB Programme management structure.
Figure 1.6 Typical organisations.
Chapter 2
Figure 2.1 Key artefacts: Stage A (Inception).
Figure 2.2 Programmes and their environments.
Figure 2.3 Overall strategic approach, UK Olympics.
Figure 2.4 Strategic change and strategic objectives by change type.
Figure 2.5 Strategic objectives alignment.
Figure 2.6 Typical programme organisation.
Chapter 3
Figure 3.1 Key artefacts: Stage B (Initiation).
Figure 3.2 Benefit categories.
Figure 3.3 Benefit delivery in three stages.
Figure 3.4 Example of representation of benefits realisation over time.
Chapter 4
Figure 4.1 Key Artefacts: Stage C (Definition).
Figure 4.2 Programme controls.
Figure 4.3 Full‐year programme expenditure example.
Figure 4.4 Programme delivery plan.
Figure 4.5 Stakeholder map.
Figure 4.6 Ability to impact and commitment to the change.
Figure 4.7 Reference Class Forecast.
Figure 4.8 Programme schedule with risks.
Figure 4.9 Change, risk and reporting.
Figure 4.10 Financial management roles and responsibilities.
Figure 4.11 Programme budget for transport programme (example).
Figure 4.12 Waterfall chart (programme funds example).
Figure 4.13 Sankey chart (programme funds example).
Figure 4.14 Delivery/project performance – programme EVM summary.
Figure 4.15 Earned value metrics.
Figure 4.16 Programme fiscal year performance (annual spend forecast).
Figure 4.17 Four‐year programme cost projection.
Figure 4.18 Reporting integration.
Figure 4.19 Invitation to tender (ITT), signed outline contract (SOC) plus v...
Figure 4.20 PMO structure, function and reporting.
Chapter 5
Figure 5.1 Key artefacts: Stage D (implementation).
Figure 5.2 Stage D: implementation.
Figure 5.3 Common construction procurement methods.
Figure 5.4 Measuring progress using S curves.
Figure 5.5 Data analysis on programmes.
Figure 5.6 Data collection on programmes.
Figure 5.7 Measuring progress on programmes.
Figure 5.8 Reporting on multiple projects in a programme.
Figure 5.9 Forecasting schedule information.
Figure 5.10 Programme monitoring and control.
Figure 5.11 Interface between programme and project reporting.
Figure 5.12 The need for independent analysis.
Figure 5.13 Correct use of graphics (example 1).
Figure 5.14 Correct use of graphics (example 2).
Figure 5.15 Programme time management.
Figure 5.16 Key points of contact.
Chapter 6
Figure 6.1 Stage E: Benefits review and transition.
Figure 6.2 Key artefacts: Stage E (Benefits realisation and transition).
Figure 6.3 Managing benefits realisation.
Figure 6.4 Benefits map Step 1: Mapping programme objectives to strategic ob...
Figure 6.5 Benefits map Step 2: Identifying and mapping benefits to programm...
Figure 6.6 Benefits map Step 3: Identifying business changes.
Figure 6.7 Benefits map Step 4: Mapping project outputs to benefits.
Figure 6.8 Benefits map Step 5: mapping the links between programme, objecti...
Figure 6.9 Organisation size over time for programme delivery.
Chapter 7
Figure 7.1 Key artefacts: Stage F (Closure).
Figure 7.2 Stage F: Closure.
Appendix B
Figure B.1 Stage review process.
Figure B.2 Fibonacci sequence.
Figure B.3 Example of planning poker.
Figure B.4 Manging using the concept of SPRINTS.
Figure B.5 Example of Kanban boards and time schedules.
Figure B.6 Programme time schedule.
Figure B.7 Example of burn‐down charts.
Figure B.8 Media wall example.
Figure B.9 Managing the programme scope.
Figure B.10 Three‐point estimate triangle.
Figure B.11 Estimation of uncertainty: illustrative example.
Figure B.12 S‐curve detailing the cumulative contingency requirement.
Figure B.13 Dataset example.
Figure B.14 Reference Class Forecasting using the manual method.
Figure B.15 Results of the manual method.
Figure B.16 Descriptive statistics (example).
Figure B.17 Frequency histogram (example).
Figure B.18 Percentiles calculation using excel.
Figure B.19 Reference class forecast (example).
Cover
Table of Contents
Title Page
Copyright
Foreword
Acknowledgements
List of Figures
Working Group (WG) of the Code of Practice for Programme Management
Glossary
Begin Reading
Appendix A: Programme Delivery Matrix
Appendix B: Tools and Techniques
Appendix C: Templates
Appendix D: Key Roles: Skills and Competencies
Bibliography
Past Working Group of the Code of Practice for Programme Management
Index
End User License Agreement
iii
iv
xiii
xiv
xv
xvii
xviii
xix
xxi
xxii
xxiii
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
19
20
21
22
23
24
25
26
27
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
73
74
75
76
77
78
79
80
81
82
83
84
85
86
87
88
89
90
91
92
93
94
95
96
97
98
99
100
101
102
103
104
105
106
107
108
109
111
112
113
114
115
116
117
118
119
120
121
122
123
124
125
126
127
128
129
130
131
132
133
134
135
136
137
138
139
140
141
142
143
144
145
147
148
149
150
151
152
153
154
155
156
157
158
159
161
162
163
164
165
166
167
Second Edition
This second edition first published 2024© 2024 John Wiley & Sons Ltd
Edition HistoryJohn Wiley & Sons Ltd (1e, 2016).
All rights reserved. No part of this publication may be reproduced, stored in a retrieval system, or transmitted, in any form or by any means, electronic, mechanical, photocopying, recording or otherwise, except as permitted by law. Advice on how to obtain permission to reuse material from this title is available at http://www.wiley.com/go/permissions.
The right of The Chartered Institute of Building to be identified as the author of this work has been asserted in accordance with law.
Registered OfficesJohn Wiley & Sons, Inc., 111 River Street, Hoboken, NJ 07030, USAJohn Wiley & Sons Ltd, The Atrium, Southern Gate, Chichester, West Sussex, PO19 8SQ, UK
For details of our global editorial offices, customer services, and more information about Wiley products visit us at www.wiley.com.
Wiley also publishes its books in a variety of electronic formats and by print‐on‐demand. Some content that appears in standard print versions of this book may not be available in other formats.
Trademarks: Wiley and the Wiley logo are trademarks or registered trademarks of John Wiley & Sons, Inc. and/or its affiliates in the United States and other countries and may not be used without written permission. All other trademarks are the property of their respective owners. John Wiley & Sons, Inc. is not associated with any product or vendor mentioned in this book.
Limit of Liability/Disclaimer of WarrantyWhile the publisher and authors have used their best efforts in preparing this work, they make no representations or warranties with respect to the accuracy or completeness of the contents of this work and specifically disclaim all warranties, including without limitation any implied warranties of merchantability or fitness for a particular purpose. No warranty may be created or extended by sales representatives, written sales materials or promotional statements for this work. This work is sold with the understanding that the publisher is not engaged in rendering professional services. The advice and strategies contained herein may not be suitable for your situation. You should consult with a specialist where appropriate. The fact that an organization, website, or product is referred to in this work as a citation and/or potential source of further information does not mean that the publisher and authors endorse the information or services the organization, website, or product may provide or recommendations it may make. Further, readers should be aware that websites listed in this work may have changed or disappeared between when this work was written and when it is read. Neither the publisher nor authors shall be liable for any loss of profit or any other commercial damages, including but not limited to special, incidental, consequential, or other damages.
Library of Congress Cataloging‐in‐Publication Data
Names: Chartered Institute of Building (Great Britain), author.Title: Code of practice for programme management in the built environment / The Chartered Institute of Building.Description: Second edition. | Hoboken, NJ : Wiley-Blackwell, 2024. | Includes bibliographical references and index.Identifiers: LCCN 2024003438 (print) | LCCN 2024003439 (ebook) | ISBN 9781394192434 (paperback) | ISBN 9781394192458 (adobe pdf) | ISBN 9781394192441 (epub)Subjects: LCSH: Building–Superintendence. | Project management.Classification: LCC TH438 .C626 2024 (print) | LCC TH438 (ebook) | DDC 658.4/04 – dc23/eng/20240212LC record available at https://lccn.loc.gov/2024003438LC ebook record available at https://lccn.loc.gov/2024003439
Cover Design: WileyCover Images: © Ashley Cooper/Getty Images; pyramid/line graphic ‐ created by Wiley ‐ concept provided by author
The Code of Practice for Programme Management was first published in 2016 and, in that relatively short time, we have seen many challenging changes in the way that built environment projects are delivered.
This second edition is a natural development from the first edition and builds on the sixth edition of the Code of Practice for Project Management published in 2022, authored by two experts with UK and international expertise in this field.
The first edition of this Code of Practice defined a programme as:
A collective of related projects is coordinated to achieve desired benefits more effectively than when managing them as a group of individual projects.
This definition has been retained for the second edition.
The term ‘Built Environment’ has been retained as we continue to see projects that are not solely construction or development‐related. Some of the client sectors, for example, highways, rail, airports, shipping or nuclear are likely to incorporate projects that are not related to construction. Accordingly, I believe that this code has relevance to a very wide reader base, which goes beyond construction.
Six core themes have been identified as key to the life cycle strategy of the programme. These are 1. developing capability, 2. procuring value, 3. digitalisation and visualisation, 4. cultural identity and ethics, 5. sustainability and its governance and 6. platform thinking.
The need for programme management arises when benefits obtained in a coordinated manner are greater than the sum of individual project benefits obtained in isolation.
This need has continued to grow due to several factors, including being seen as a way to help transform the industry as a whole, which has continued to struggle with productivity, collaboration and innovation. In addition, it is seen as an opportunity to manage the availability of resources and skills in the industry and obtain wider beneficial societal change beyond solely the strategic objectives of the client organisation.
As this second edition was being prepared, society was experiencing major disruptions, including the pandemic, high inflation and a war on the borders of Europe. These global issues are influencing the energy supply. This is at the same time as environmental challenges and an ongoing emphasis on social value and sustainability.
All this points to a current and future operating environment that is more uncertain than we have experienced in recent times.
These changes provide a greater emphasis on the application of programme management becoming more dynamic, which requires actively organising and managing.
I believe the application of this Code of Practice can assist those responsible for programmes in this rapidly changing world. It will also serve as an important textbook reference in academia.
I thank all those involved in the production of this code who have offered advice and guidance as this edition was being written. My special thanks to those who have spent time reviewing and commenting on the work of the authors. I also thank colleagues at CIOB for their work in coordinating the numerous parts of the code.
Mike Foy OBE FCIOB MBA FCMI
CIOB President 2021/2022
I am delighted that the Chartered Institute of Building is publishing this updated version of the Code of Practice for Programme Management. As Past President Mike Foy mentions in his foreword, the built environment and construction sector are ever‐changing, and there is perhaps more need than ever to look to the role of Programme Manager, with their overview of work and the opportunity to anticipate potential changes.
The previous edition of this code of practice was ably steered by CIOB Fellows and other industry experts, who focused on producing a practical document for a discipline that is present in many different sectors. CIOB is a broad church, covering an impressive range of built environment sector roles and, in turn, this publication is intended for an audience of programme management professionals who are active across a range of industries.
The process to update this second edition of our Code of Practice for Programme Management reflects both the depth of expertise of the profession and the breadth of sectors it spans, with contributions from built environment specialists and other professional institutions providing their insights and expertise.
A list of participants and the organisations represented is included in this book. I want to take this opportunity to thank all the CIOB members who contributed their time in producing this revised Code of Practice for Programme Management. I also want to acknowledge all those who have supported our publications over the years – our community of members who contribute to our publications has always been generous in sharing their time and expertise.
Caroline Gumble
Chief Executive
Chartered Institute of Building
1.1 Programme Delivery Triangle
1.2 Organisational interfaces in the programme context
1.3 Six themes for programme management in the built environment
1.4 Programme, projects and benefits
1.5 CIOB Programme management structure
1.6 Typical organisations
2.1 Key artefacts: Stage A (Inception)
2.2 Programmes and their environments
2.3 Overall strategic approach, UK Olympics
2.4 Strategic change and strategic objectives by change type
2.5 Strategic objectives alignment
2.6 Typical programme organisation
3.1 Key artefacts: Stage B (Initiation)
3.2 Benefit categories
3.3 Benefit delivery in three stages
3.4 Example of representation of benefits realisation over time
4.1 Key Artefacts: Stage C (Definition)
4.2 Programme controls
4.3 Full‐year programme expenditure example
4.4 Programme delivery plan
4.5 Stakeholder map
4.6 Ability to impact and commitment to the change
4.7 Reference Class Forecast
4.8 Programme schedule with risks
4.9 Change, risk and reporting
4.10 Financial management roles and responsibilities
4.11 Programme budget for transport programme (example)
4.12 Waterfall chart (programme funds example)
4.13 Sankey chart (programme funds example)
4.14 Delivery/project performance – programme EVM summary
4.15 Earned value metrics
4.16 Programme fiscal year performance (annual spend forecast)
4.17 Four‐year programme cost projection
4.18 Reporting integration
4.19 Invitation to tender (ITT), signed outline contract (SOC) plus value of contract placed
4.20 PMO structure, function and reporting
5.1 Key artefacts: Stage D (implementation)
5.2 Stage D: implementation
5.3 Common construction procurement methods
5.4 Measuring progress using S curves
5.5 Data analysis on programmes
5.6 Data collection on programmes
5.7 Measuring progress on programmes
5.8 Reporting on multiple projects in a programme
5.9 Forecasting schedule information
5.10 Programme monitoring and control
5.11 Interface between programme and project reporting
5.12 The need for independent analysis
5.13 Correct use of graphics (example 1)
5.14 Correct use of graphics (example 2)
5.15 Programme time management
5.16 Key points of contact
6.1 Stage E: Benefits review and transition
6.2 Key artefacts: Stage E (Benefits realisation and transition)
6.3 Managing benefits realisation
6.4 Benefits map Step 1: Mapping programme objectives to strategic objectives
6.5 Benefits map Step 2: Identifying and mapping benefits to programme objectives
6.6 Benefits map Step 3: Identifying business changes
6.7 Benefits map Step 4: Mapping project outputs to benefits
6.8 Benefits map Step 5: mapping the links between programme, objectives, benefits, business changes and project outputs
6.9 Organisation size over time for programme delivery
7.1 Key artefacts: Stage F (Closure)
7.2 Stage F: Closure
B.1 Stage review process
B.2 Fibonacci sequence
B.3 Example of planning poker
B.4 Manging using the concept of SPRINTS
B.5 Example of Kanban boards and time schedules
B.6 Programme time schedule
B.7 Example of burn‐down charts
B.8 Media wall example
B.9 Managing the programme scope
B.10 Three‐point estimate triangle
B.11 Estimation of uncertainty: illustrative example
B.12 S‐curve detailing the cumulative contingency requirement
B.13 Dataset example
B.14 Reference Class Forecasting using the manual method
B.15 Results of the manual method
B.16 Descriptive statistics (example)
B.17 Frequency histogram (example)
B.18 Percentiles calculation using excel
B.19 Reference class forecast (example)
Chair
Michael J Foy
OBE, FCIOB, MBA, FCMI
Working Group Chair, CIOB President 2021/2022
Technical Authors
Dr. Tahir Hanif
FCIOB, FAPM, FACostE, FIC FRICS
Principal PMO and Project Controls Consultant – Costain; Honorary Professor ‐ University of the West of Scotland
Dr. Simon Addyman
MSc, PhD, FAPM
Associate Professor of Project Management, UCL
Working Group
Gildas André
MBA, MSc, BSc (Hons), MAPM, MCIOB, Director GAN Advisory Services
David Haimes
MCIOB
David Haimes Consulting Limited
Dr. Ruth Murray‐Webster
HonFAPM
Director, Potentiality UK
Niki French
FICE
Head of Utilities, HS2
Andy Stanley
FCIOB, FAPM, AMICE, NECReg
Programme Management Practitioner.
Dr. Paul Sayer
Publisher: John Wiley & Sons Limited
Dr. Ashwini Konanahalli
BArch, MSc, PhD, FHEA
Reader in Construction Management, University of the West of Scotland
The following also contributed in the development of the Code of Practice for Programme Management.
Stephen Coppin
BEng(Hons) MSc C.Build E FCABE FCIOB CFIOSH FIIRSM FMaPS CWIFM MInstRE PIEMA EurOHSM
Strategic Technical Director, SJC Risk Management Solutions Ltd
David Philp
MSc, BSc, FCIOB FICE FRICS FCInstCES
Chief Value Officer, Cohesive Group
Jamie Strathearn
MRICS MCIOB
Head of Programme, Cost, Procurement, Pre‐Construction ‐ Marks and Spencer
Francis Ho
FCIOB
Partner at Charles Russell Speechlys LLP
Milan Radosavljevic
PhD UDIG MIZS‐CEng
Vice‐Principal and Pro Vice‐Chancellor (Research, Innovation and Engagement)
Mr. Wes Beaumont
BSc, MSc, MCIOB
Associate Vice‐President, Digital Transformation Leader, AECOM US
Neil Thompson
FIET, MCIOB, MDAMA
Director, AtkinsRealis
Bill McElroy
FAPM, FICE
Independent Consultant
Benefits
A (directly or indirectly) measurable improvement resulting from an outcome perceived as an advantage by one or more stakeholders and that contributes towards one or more organisational strategic objective(s).
Benefits management
The identification, definition, monitoring, realisation and optimisation of benefits within and beyond a programme.
Benefits profile
Used to define each benefit (and dis‐benefit) and provide a detailed understanding of what will be involved and how the benefit will be realised.
Benefits realisation manager (BRM)
Supports programme manager by taking the responsibility for benefits identification, mapping and realisation – ensures that necessary business benefits are realised.
Benefits realisation plan
Used to monitor the realisation of benefits across the programme and set governing controls.
Business change manager (BCM)
Responsible for ensuring that the objectives have been sufficiently and accurately defined, managing the transition activities and undertaking and determining whether the intended benefits have been realised.
Business partner
Organisations that have a business or financial interest in the outcome of the programme.
Clients
Persons using the services of a professional entity or those who are procuring products or services from a professional entity. In legal context, a client may instruct a professional entity to act on the client's behalf. In the programme sense, this document defines clients as ‘the body or group that procures the services of professionals to initiate and deliver projects or a programme of projects’.
Customer
Persons who are paying for a product or a service but not necessarily in the legal context represented by the professional entity.
Deliverable
What is to be provided as a result of an initiative or project – typically tangible and measurable.
Disbenefit
A (directly or indirectly) measurable decline resulting from an outcome perceived as negative by one or more stakeholders that may or may not affect one or more organisational strategic objective(s).
Issue
A relevant event that has happened or is likely to happen was not planned and requires management action.
Opportunity
A relevant but uncertain event that can have a favourable impact on objectives or benefits.
Outcome
The result of a change. Outcomes are desired when a change is conceived and are achieved as a result of the activities undertaken to reflect the change.
Output
The tangible or intangible effect of a planned activity or initiative.
Portfolio
A portfolio is a total collection of programmes and/or stand‐alone projects managed by an organisation to achieve strategic objectives.
Programme
A programme is a collective of related projects coordinated to achieve desired benefits not possible from managing them as a group of individual projects.
Programme brief
Used to assess whether the programme is viable and achievable.
Programme communication manager
Supports the programme manager by managing all internal and external communication channels, developing the programme communications plan and ensuring governance of internal and external communication protocols.
Programme delivery plan (PDP)
A detailed description of what the programme will deliver, how and when it will be achieved and the financial implications of its delivery and implementation.
Programme financial manager
Deals with complex financial issues including funding arrangements, cash flow and financial governance. Responsible for programme financial plan, budget and financial reporting.
Programme financial plan
A financial statement that collects all the costs that have been identified in relation to implementing the programme – often the funding streams are also identified in this document.
Programme management board
A group established to support a programme sponsor in delivering a programme.
Programme management office (PMO)
The function providing information and governance for a programme and its delivery objectives – it can provide support to more than one programme.
Programme manager
The role responsible for the setup, management and delivery of a programme – typically allocated to a single individual; for large and complex programmes an organisation can be given this role.
Programme mandate
Expansion of the vision statement setting out in greater detail what it is that the programme needs to achieve in terms of the outcomes and what it is that the programme seeks to deliver.
Programme monitor
In certain privately funded programmes, a programme monitor (sometimes known as funder/lender/investor's advisor or monitor) may be appointed, on behalf of the funding entities, to safeguard the interests of the funders.
Programme sponsor
The main driving force behind a programme, appointed by the client and the point of accountability for the programme.
Programme sponsor's board
The driving group behind the programme, which provides the investment decisions and senior‐level governance for the rationale and objectives of the programme.
Programme timescale plan
An overall delivery time schedule for the programme.
Project
A project is a temporary and transient undertaking created to achieve agreed objectives and produce and deliver a product, service or result
Risk
An uncertain event or set of events that, if it occurs, has an effect on the achievement of the objectives. A risk is measured by a combination of the probability of a perceived threat or opportunity occurring and the magnitude of its impact on objectives.
Stakeholder
Any individual, group or organisation that can affect, be affected by or perceive itself to be affected by a programme.
Transition
The changes that need to take place in business as usual, which are aimed to be managed, as project outputs are exploited in order to achieve programme outcomes.
Transition plan
The schedule of activities to cover the transition phase of the benefits realisation plan.
Value
The total sum of benefits to be derived from the programme less the total costs expended across the life of the business case.
Vision
A view of a better future that will be delivered by the programme.
Vision statement
A business vision for change setting out the intent and the benefits sought.
This second edition of the Code of Practice for Programme Management in the Built Environment is a natural development from the first edition and builds on the recently published sixth edition of the highly successful Code of Practice for Project Management for the Built Environment.
The first edition of this Code of Practice defined a programme as:
a collective of related projects coordinated to achieve desired benefits more effectively than when managing them as a group of individual projects.
In this second edition, we retain this definition. In some organisations, programmes are created with a single business case aligned to a set of benefits. While for others, business cases and benefits are defined at project and not programme level. However, in both cases, the projects are delivered as a programme in order to achieve an organisation's strategic objectives more effectively.
We have retained ‘for the built environment’ because we continue to see many projects that are not solely construction or development‐related. For example, if we consider some of the client sectors involved in creating new facilities and/or infrastructure, such as highways, rail, airports, shipping, nuclear, etc., all of these are likely to incorporate projects that are not related to construction. These may include disciplines such as information technology,