37,99 €
This key text for the building team is an authoritative guide and gives a detailed account of the team's roles and responsibilities, with best industry practice required to ensure that building projects meet clients' expectations on time, cost and quality. The second edition of The Aqua Group Guide to Procurement, Tendering and Contract Administration has been edited, enlarged and updated by a high-profile author team with unparalleled experience of both private and public sectors, as well as of teaching on QS courses. It covers the entire building process from inception to final account and throughout, the emphasis is on current best practice. This edition has new material on the CDM regulations; JCT contracts; the RIBA Plan of Work; the RICS New Rules of Measurement; BIM; and Sustainability - as well as a general update for industry changes, especially on procurement; internationalisation; and PFI. With clear and thorough explanations, you are taken through self-contained chapters covering the detail of the briefing stage, procurement methods, tendering procedures, and contract administration. The period from starting a college course to successful completion of professional examinations represents a long and steep learning curve. The range of skills and the knowledge required to perform work efficiently and effectively might, at first, seem rather daunting. Although designed as an introductory textbook for undergraduates in construction, architecture and quantity surveying, The Aqua Group Guide offers an excellent overview of contract administration and will provide you with sufficient understanding to hold you in good stead for your early years in professional practice.
Sie lesen das E-Book in den Legimi-Apps auf:
Seitenzahl: 660
Veröffentlichungsjahr: 2016
Cover
Title Page
Copyright
Part I: Briefing the Project Team
Chapter 1: The Project Team
Introduction
Parties to a building contract and their supporting teams
Rights, duties and responsibilities
Statutory requirements
Avoiding disputes
Communications
Chapter 2: Assessing the Needs
The structure
The strategic definition
Contribution to the initial project brief
The initial programme
The appointment
Chapter 3: Buildings as Assets
Buildings as assets as well as buildings
Single building or programme?
Buildings as solutions to business challenges?
Everyday solutions-based thinking
Summary
Part II: Available Procurement Methods
Chapter 4: Principles of Procurement
Simple theory – complex practice
The eternal triangle
Other considerations
Entering into the contract
The dynamics of tendering
Chapter 5: Basic Concepts
Economic use of resources
Contractor's contribution to design and contract programme
Production cost savings
Continuity
Risk and accountability
Summary
Chapter 6: Accountability
Background
The modern concept of public accountability
Contract documentation
Proper price
Dispensing with competition
Inflation
Value for money
Summary
Chapter 7: Value and Risk Management
Value management
Risk management
Risk management strategies
Allocating management actions
Value and risk are complementary
Chapter 8: Fixed Price and Cost Reimbursement
Fixed price
Cost reimbursement
Application to contract elements
Fluctuations
Target cost contracts
Use
Programme
Summary
Chapter 9: Fixed Price Contracts
JCT fixed price contracts
Advantages and disadvantages of fixed price contracts
Chapter 10: Cost Reimbursement Contracts
The fee
The prime cost building contract
Advantages and disadvantages of cost reimbursement contracts
Budget and cost control
Administering the contract
Procedure for keeping prime costs
Sub-letting
Defective work
Cost control
Final account
Chapter 11: Target Cost Contracts
Guaranteed maximum price contracts
Competition
Contract
Advantages and disadvantages
Use
Chapter 12: Management and Construction Management Contracts
Payment and cost control
Selection and appointment of the contractor
Contract conditions
Contract administration
Professional advisers
Advantages and disadvantages
Construction management
Use
Programme
Chapter 13: Design and Build Contracts
The contract
Where to use DB (and when not to do so)
Managing the design process
Novation
Evaluation of submissions
Post-contract administration
Financial administration
Programme
Advantages and disadvantages
Chapter 14: Continuity Contracts
Serial contracting
Continuation contracts
Term contracts
Chapter 15: Partnering
A definition
When to adopt a partnering approach
The agreement
JCT Partnering Charter
JCT Framework Agreement
JCT constructing excellence
The partnering workshop
The benefits
The risks
Future of partnering
Chapter 16: EU Procurement
Introduction
The scope of procurement law
The general principles
Procedures
Key principles
Evaluating tenderers
Evaluating tenders
Framework agreements
Contract change
Cancellation of the process
Information obligations debrief and disclosure
Commencing proceedings
Remedies
Complaints to the EU commission and other challenge procedures
Tendering contracts
Notes
Part III: Preparing for and Inviting Tenders
Chapter 17: Procedure from Brief to Tender
Initial brief
Procurement
Detailed design
Programming
Design team meetings
Drawings
Specifications
Bills of quantities
Specialist sub-contractors and suppliers
Quality assurance
Obtaining tenders
Chapter 18: Pre-Contract Cost Control
Introduction
The purpose of pre-contract cost control
Framework for pre-contract estimating
Order of cost estimate
Information used to prepare an order of cost estimate
Treatment of on-costs and other costs in order of cost estimates
Presenting an order of cost estimate
Cost plans
Treatment of on-costs and other costs in cost plans
Presenting a cost plan
Challenges associated with the production of cost plans
Cash flow
Whole life costs
Summary
Notes
Chapter 19: Drawings and Schedules
The language of drawing
The changing role of drawings and documents
Quality
Types, sizes and layout of drawings
Nature and sequence of drawing production
Computer aided design
Project extranets
Contents of drawings
Schedules
Drawings and schedules for records
Notes
Chapter 20: Specifications
The use of specifications
Specification writing
Chapter 21: Building Information Modelling
The BIM revolution – what is BIM, and who/what is it for?
The role of government and its BIM strategy
The levels of BIM adoption
The BIM journey
Level 3 and the future
Epilogue
Notes
Chapter 22: Bills of Quantities
Tender and contract document
The wider role
Basic information
Preliminaries
Preambles
Measured works
Formats
Chapter 23: Sub-contractors
Introduction
Specialist sub-contractors
Design by the sub-contractor
The SBC and sub-contract agreements
Chapter 24: Obtaining Tenders
Introduction
Tender list
Preliminary enquiry
Tender documents and invitation
Tender period
Tender compliance
Late tenders
Opening tenders
Examination and adjustment of the priced document
Negotiated reduction of a tender
Notification of results
Tender analysis
E-Tendering
Part IV: Contract Administration
Chapter 25: Placing the Contract
Preparing and signing the contract documents
Performance bonds and parent company guarantees
Collateral warranties
Third party rights
Issue of documents
Insurances
Chapter 26: Meetings
Initial meeting
Procedure to be followed at subsequent meetings
Contractor's meetings
Employer's meetings
Chapter 27: Site Duties
The architect on site
The architect's duty of inspection and supervision
Considerate constructors scheme
Site safety
Fire precautions on site
Chapter 28: Instructions
Architect/contract administrator's instructions
Clerk of works' directions
Format and distribution of instructions
Chapter 29: Variations and Post-Contract Cost Control
Variations
Valuing variations
Cost control
Chapter 30: Interim Payments
Introduction
Certificates and payments under the SBC
Interim certificates under the SBC
Retention under the SBC
Payments to sub-contractors under the SBC
Value added tax
Valuation and certificate forms
Chapter 31: Completion, Defects and the Final Account
Practical completion
Partial possession
Possession of the building
Defects and making good
Final account
Final certificate
Chapter 32: Delays and Disputes
Introduction
Delays caused by the contractor
Delays caused by the employer or his representatives
Delays caused by events outside the control of either party
SBC procedure in the event of delay
Reimbursement of loss and/or expense under the SBC
Liquidated damages
Disputes and dispute resolution
Chapter 33: An Introduction to Sustainability in Construction
Sustainable development
The regulatory framework for construction
Assessing the sustainability of construction and buildings
Sustainable procurement
Other important issues
References
Chapter 34: Future Trends
Global -v- local
Industry and corporate trends
Opportunities and challenges
Index
End User License Agreement
1
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
27
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
83
84
85
86
87
88
89
90
91
92
93
94
95
96
97
98
99
100
101
102
103
104
105
106
107
108
109
110
111
112
113
114
115
116
117
118
119
120
121
122
123
124
125
126
127
128
129
130
131
133
134
135
136
137
138
139
140
141
142
143
144
145
146
147
148
149
150
151
152
153
154
155
156
157
158
159
160
161
162
163
164
165
166
167
168
169
170
171
172
173
174
175
176
177
178
179
180
181
182
183
184
185
186
187
188
189
190
191
192
193
194
195
196
197
198
199
200
201
202
203
204
205
206
207
208
209
210
211
212
213
214
215
216
217
218
219
220
221
222
223
224
225
226
227
228
229
230
231
233
234
235
236
237
238
239
240
241
242
243
244
245
246
247
248
249
250
251
252
253
254
255
256
257
258
259
260
261
262
263
264
265
266
267
268
269
270
271
272
273
274
275
276
277
278
279
280
281
282
283
284
285
286
287
288
289
290
291
292
293
294
295
296
297
298
299
300
301
302
303
304
305
306
307
308
309
310
311
312
313
314
315
316
317
318
319
320
321
322
323
324
325
326
327
328
329
330
331
332
333
334
335
336
337
338
339
340
341
342
343
344
345
346
347
348
349
350
351
352
353
354
355
356
357
358
359
360
361
362
363
364
365
366
367
368
Cover
Table of Contents
Begin Reading
Chapter 2: Assessing the Needs
Figure 2.1 RIBA outline plan of work. Reproduced by permission of Royal Institute of British Architects.
Example 2.1 The initial programme.
Chapter 4: Principles of Procurement
Figure 4.1 The procurement triangle.
Figure 4.2 Variations on the eternal triangle, showing the different priorities.
Example 4.1 Procurement options
Chapter 7: Value and Risk Management
Figure 7.1 Optimising value for money.
Figure 7.2 Opportunities reduce with time.
Figure 7.3 The integrated process of risk and value management.
Chapter 8: Fixed Price and Cost Reimbursement
Figure 8.1 Sequence of events – fixed price and cost reimbursement.
Chapter 11: Target Cost Contracts
Example 11.1 Target cost contract with saving
Example 11.2 Target cost contract with overspend
Example 11.3 Target cost contract with cost saving and overspend
Chapter 12: Management and Construction Management Contracts
Figure 12.1 Differing contractual arrangements.
Figure 12.2 Comparative sequence of events.
Chapter 13: Design and Build Contracts
Figure 13.1 Differing processes compared.
Chapter 15: Partnering
Figure 15.1 The three fundamental characteristics of partnering.
Chapter 18: Pre-Contract Cost Control
Figure 18.1 Constituents of an order of cost estimate.
Figure 18.2 Upper floors element hierarchy.
Figure 18.3 Constituents of a cost plan.
Chapter 19: Drawings and Schedules
Example 19.1 Window schedule
Example 19.2 Door schedule
Example 19.3 Finishings schedule
Example 19.4 Manhole schedule
Chapter 20: Specifications
Figure 20.1 Uniclass section J (RIBA enterprise).
Chapter 21: Building Information Modelling
Figure 21.1 BIM maturity diagram.
Chapter 22: Bills of Quantities
Example 22.1 Uniclass work section bill of quantities
Example 22.2 Locational bill of quantities
Example 22.3 Annotated bills of quantities
Example 22.4 Elemental bills of quantities
Chapter 25: Placing the Contract
Example 25.1 Performance bond
Example 25.2 Parent company guarantee
Chapter 26: Meetings
Example 26.1 Construction programme
Example 26.2 Typical site meeting agenda
Example 26.3 Typical site meeting minutes
Chapter 27: Site Duties
Example 27.1 Standard checklist for site inspections
Chapter 28: Instructions
Example 28.1 Architect's instruction. Reproduced by permission of Royal Institute of British Architects.
Chapter 29: Variations and Post-Contract Cost Control
Example 29.1 Financial review. Reproduced by permission of Royal Institute of British Architects.
Chapter 30: Interim Payments
Example 30.1 Interim valuation.
Example 30.2 Statement of retention.
Example 30.3 Interim certificate.
Chapter 31: Completion, Defects and the Final Account
Example 31.1 Certificate of practical completion.
Example 31.2 Certificate of making good defects.
Example 31.3 Final certificate.
Chapter 32: Delays and Disputes
Example 32.1 Revision to completion date. Reproduced by permission of Royal Institute of British Architects.
Chapter 34: Future Trends
Figure 34.1 Team interactivity.
Chapter 7: Value and Risk Management
Table 7.1 Three phases in applying value management
Table 7.2 The stages of value management
Table 7.3 Study structure
Table 7.4 Evolution of risk management studies
Chapter 9: Fixed Price Contracts
Table 9.1 JCT forms of contract
Chapter 18: Pre-Contract Cost Control
Table 18.1 Alignment of estimates and cost plans and project stages
Table 18.2 Information requirement for the production of an order of cost estimate
Table 18.3 Information requirement for the production of cost plan 1
Chapter 29: Variations and Post-Contract Cost Control
Table 29.1 The five basic methods for the valuation of variations (excluding variations relating to a CDP and Schedule 2 Quotation)
Table 29.2 The valuation of variations relating to a CDP
Second Edition
Edited by
Mark Hackett and Gary Statham
with contributions from
Michael Bowsher, John Connaughton, Michael Dallas, Paul Morrell, Alan Muse, Erland Rendall, Simon Rawlinson, Nick Schumann, Andrew Shaw and Peter Ullathorne
This edition first published 2016
© 2016 by John Wiley & Sons Ltd
© 2007 The Aqua Group and Blackwell Publishing
Wiley-Blackwell is an imprint of John Wiley & Sons, formed by the merger of Wiley's global Scientific, Technical and Medical business with Blackwell Publishing.
First edition published 2007
Second edition published 2016
Registered office
John Wiley & Sons, Ltd, The Atrium, Southern Gate, Chichester, West Sussex, PO19 8SQ, United Kingdom.
Editorial offices:
9600 Garsington Road, Oxford, OX4 2DQ, United Kingdom.
The Atrium, Southern Gate, Chichester, West Sussex, PO19 8SQ, United Kingdom.
For details of our global editorial offices, for customer services and for information about how to apply for permission to reuse the copyright material in this book please see our website at www.wiley.com/wiley-blackwell.
The right of the author to be identified as the author of this work has been asserted in accordance with the UK Copyright, Designs and Patents Act 1988.
All rights reserved. No part of this publication may be reproduced, stored in a retrieval system, or transmitted, in any form or by any means, electronic, mechanical, photocopying, recording or otherwise, except as permitted by the UK Copyright, Designs and Patents Act 1988, without the prior permission of the publisher.
Designations used by companies to distinguish their products are often claimed as trademarks. All brand names and product names used in this book are trade names, service marks, trademarks or registered trademarks of their respective owners. The publisher is not associated with any product or vendor mentioned in this book.
Limit of Liability/Disclaimer of Warranty: While the publisher and author(s) have used their best efforts in preparing this book, they make no representations or warranties with respect to the accuracy or completeness of the contents of this book and specifically disclaim any implied warranties of merchantability or fitness for a particular purpose. It is sold on the understanding that the publisher is not engaged in rendering professional services and neither the publisher nor the author shall be liable for damages arising herefrom. If professional advice or other expert assistance is required, the services of a competent professional should be sought.
Library of Congress Cataloging-in-Publication Data
The Aqua Group guide to procurement, tendering and contract administration.— Second edition / edited by Mark Hackett, Gary Statham ; with contributions from Michael Bowsher [and 5 others].
pages cm
Includes bibliographical references and index.
ISBN 978-1-118-34654-9 (paperback)
1. Buildings— Specifications. 2. Construction contracts— Great Britain. 3. Letting of contracts— Great Britain. 4. Construction industry— Management. I. Hackett, Mark, 1962- editor. II. Statham, Gary, editor.
TH425.A678 2015
692— dc23
2015008101
A catalogue record for this book is available from the British Library.
Wiley also publishes its books in a variety of electronic formats. Some content that appears in print may not be available in electronic books.
Cover design by Workhaus
Since the first editions of the Aqua Group's books, the process of constructing and running a built asset has become increasingly complicated. From inception to completion, through site acquisition, design, tender, contract and construction, each stage of the process is time-consuming and can be considerably expensive. The need to optimise the process is of paramount importance and the best base from which to achieve this is proper and efficient team work. It is therefore vital that all members of the project team are fully conversant, not only with their own role but also with the roles of others and with the inter-relationships at each stage of the project. All members of the project team can then play their part fully and effectively, contributing their particular expertise whenever required.
The make-up of any particular project team will depend upon the scope and complexity of the project, the procurement route and the contractual arrangements selected. There are already many different methods of managing a project and, no doubt, others will be developed in the future. This chapter is set in the context of traditional procurement and, although not exhaustive, provides an indication of the principles involved and the criteria by which other situations can be evaluated.
The parties to a building contract are the employer and the contractor. Those appointed by these two will complete the project team which can include:
Lesen Sie weiter in der vollständigen Ausgabe!
Lesen Sie weiter in der vollständigen Ausgabe!
Lesen Sie weiter in der vollständigen Ausgabe!
Lesen Sie weiter in der vollständigen Ausgabe!
Lesen Sie weiter in der vollständigen Ausgabe!
Lesen Sie weiter in der vollständigen Ausgabe!
Lesen Sie weiter in der vollständigen Ausgabe!
Lesen Sie weiter in der vollständigen Ausgabe!
Lesen Sie weiter in der vollständigen Ausgabe!
Lesen Sie weiter in der vollständigen Ausgabe!
Lesen Sie weiter in der vollständigen Ausgabe!
Lesen Sie weiter in der vollständigen Ausgabe!
Lesen Sie weiter in der vollständigen Ausgabe!
Lesen Sie weiter in der vollständigen Ausgabe!
Lesen Sie weiter in der vollständigen Ausgabe!
Lesen Sie weiter in der vollständigen Ausgabe!
Lesen Sie weiter in der vollständigen Ausgabe!
Lesen Sie weiter in der vollständigen Ausgabe!
Lesen Sie weiter in der vollständigen Ausgabe!
Lesen Sie weiter in der vollständigen Ausgabe!
Lesen Sie weiter in der vollständigen Ausgabe!
Lesen Sie weiter in der vollständigen Ausgabe!
Lesen Sie weiter in der vollständigen Ausgabe!
Lesen Sie weiter in der vollständigen Ausgabe!
Lesen Sie weiter in der vollständigen Ausgabe!
Lesen Sie weiter in der vollständigen Ausgabe!
Lesen Sie weiter in der vollständigen Ausgabe!
Lesen Sie weiter in der vollständigen Ausgabe!
Lesen Sie weiter in der vollständigen Ausgabe!
Lesen Sie weiter in der vollständigen Ausgabe!
Lesen Sie weiter in der vollständigen Ausgabe!
Lesen Sie weiter in der vollständigen Ausgabe!
Lesen Sie weiter in der vollständigen Ausgabe!
Lesen Sie weiter in der vollständigen Ausgabe!
Lesen Sie weiter in der vollständigen Ausgabe!
Lesen Sie weiter in der vollständigen Ausgabe!
Lesen Sie weiter in der vollständigen Ausgabe!
Lesen Sie weiter in der vollständigen Ausgabe!