77,99 €
Disruption of a construction project is of key concern to the contractor as any delay to the project will involve the contractor in financial loss, unless those losses can be recovered from the employer. It is, however, acknowledged that disruption claims in construction are difficult to prove, usually the result of poor or inaccurate project records, but the cost of lost productivity or reduced efficiency to the contractor under these circumstances is very real. Practical Guide to Disruption and Productivity Loss on Construction & Engineering Projects is clearly written to explain the key causes of disruption and productivity loss. Disruption claims rest on proof of causation, so it discusses the project records that are necessary to demonstrate the causes of disruption, lost productivity and reduced efficiency in detail. Quantification of a disruption claim in terms of delay to activities and the associated costs are also fully discussed. With many worked examples throughout the text, this will be an essential book for anyone either preparing or assessing a disruption and loss of productivity claims, including architects, contract administrators, project managers and quantity surveyors as well as contractors, contracts consultants and construction lawyers.
Sie lesen das E-Book in den Legimi-Apps auf:
Seitenzahl: 380
Veröffentlichungsjahr: 2015
Cover
Title page
Preface
Acknowledgements
Chapter 1: Introduction
1.1 Introduction
1.2 The aims of this book
1.3 Appendix 3: Society of Construction Law: Delay & Disruption Protocol (October 2002) The SCL Protocol
1.4 Conclusion
Chapter 2: Contracts and Case Law
2.1 Introduction
2.2 Contracts
2.3 Case law
Chapter 3: Planning, Programmes and Record Keeping
3.1 Background and history of planning
3.2 Planning and programming
3.3 Programme submission, review and acceptance
3.4 Programme updates and revisions
3.5 Progress records and other record keeping
Chapter 4: Delay, Disruption and Causation
4.1 Delay
4.2 Disruption
4.3 Causation
Chapter 5: Loss of Productivity
5.1 Introduction
5.2 Productivity and efficiency
5.3 Common causes of loss of efficiency
5.4 Methods of productivity measurement
Chapter 6: Acceleration and Mitigation
6.1 Acceleration
6.2 Mitigation
Appendix 1: Definitions and Glossary
Appendix 2: Standards for the Levels of a Programme or Schedule
Client’s or owner’s programme/schedule
2 Proposed levels of programme/schedule for a single project
3 Smaller Projects
4 Proposed Levels of Programme/Schedule for a Group or Programme of Projects
5 Important Associated Considerations
Appendix 3: Society of Construction Law
Guidance Clauses
Index
Also Available from Wiley Blackwell
End User License Agreement
Chapter 03
Figure 3.1 Example of a simple barchart.
Figure 3.2 Activity-on-Arrow network.
Figure 3.3 Activity-on-Node network.
Figure 3.4 Time-scaled logic-linked programme.
Figure 3.5 Activities on the critical path.
Figure 3.6 A Line of Balance chart.
Figure 3.7 A Time Chainage chart.
Figure 3.8 ‘Progress Indicator’ chart.
Figure 3.9 ‘Planned Progress’ chart.
Figure 3.10 ‘Progress Tracking’ chart.
Figure 3.11 ‘Line of Balance’ chart.
Cover
Table of Contents
Begin Reading
iii
iv
vii
ix
1
2
3
4
5
6
7
8
9
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
83
84
85
86
87
88
89
90
91
92
93
94
95
96
97
98
99
100
101
102
103
104
105
106
107
108
109
110
111
112
113
114
115
116
117
118
119
120
121
122
123
124
125
126
127
128
129
130
131
132
133
134
135
136
137
138
139
140
141
142
143
144
145
146
147
148
149
150
151
152
153
154
155
156
157
158
159
160
161
162
163
164
165
166
167
169
170
171
172
173
174
175
177
178
179
180
181
182
183
184
185
187
188
189
191
192
193
194
195
196
Roger Gibson
This edition first published 2015© 2015 by John Wiley & Sons, Ltd.
Registered OfficeJohn Wiley & Sons, Ltd, The Atrium, Southern Gate, Chichester, West Sussex, PO19 8SQ, United Kingdom.
Editorial Offices9600 Garsington Road, Oxford, OX4 2DQ, United Kingdom.The Atrium, Southern Gate, Chichester, West Sussex, PO19 8SQ, United Kingdom.
For details of our global editorial offices, for customer services and for information about how to apply for permission to reuse the copyright material in this book please see our website at www.wiley.com/wiley-blackwell.
The right of the author to be identified as the author of this work has been asserted in accordance with the UK Copyright, Designs and Patents Act 1988.
All rights reserved. No part of this publication may be reproduced, stored in a retrieval system, or transmitted, in any form or by any means, electronic, mechanical, photocopying, recording or otherwise, except as permitted by the UK Copyright, Designs and Patents Act 1988, without the prior permission of the publisher.
Designations used by companies to distinguish their products are often claimed as trademarks. All brand names and product names used in this book are trade names, service marks, trademarks or registered trademarks of their respective owners. The publisher is not associated with any product or vendor mentioned in this book.
Limit of Liability/Disclaimer of Warranty: While the publisher and author(s) have used their best efforts in preparing this book, they make no representations or warranties with respect to the accuracy or completeness of the contents of this book and specifically disclaim any implied warranties of merchantability or fitness for a particular purpose. It is sold on the understanding that the publisher is not engaged in rendering professional services and neither the publisher nor the author shall be liable for damages arising herefrom. If professional advice or other expert assistance is required, the services of a competent professional should be sought.
Library of Congress Cataloging-in-Publication Data
Gibson, Roger, 1944– author.Practical guide to disruption and productivity loss on construction and engineering projects / Roger Gibson. pages cm Includes index.
ISBN 978-0-470-65743-0 (hardback)1. Construction contracts–Great Britain. I. Title. KD1641.G53 2015 343.4107′8624–dc23
2014032112
A catalogue record for this book is available from the British Library.
Wiley also publishes its books in a variety of electronic formats. Some content that appears in print may not be available in electronic books.
I have been involved in the construction industry in the UK and overseas for over 50 years, both at project level in planning and project positions and in head-office organisations in managerial roles. During this time, and in particular during the last 20 years which I have spent primarily in time-related disputes and claims, I have become increasingly aware of the lack of a comprehensive, easy to understand, practical and ‘down to earth’ reference book for those involved in the preparation and assessment of disruption and loss of productivity claims.
The views expressed by me in this book represent many years’ experience of looking at projects that have gone wrong and resulted in a dispute(s) between the parties. In practice, many projects are completed without major claims, and where these do occur they are settled promptly and professionally without escalating into a formal dispute. Unfortunately, a claim that evolves into a formal dispute often stretches the resources of the parties and their consultants and can add financial pressure in resolving the dispute.
Many construction firms, large and small alike, lack staff with the skills required to produce well-presented disrupted and loss of productivity claims. Similarly, the receiving party, architect, engineer or employer, often does not have the in-house skills to review such submissions and claims thoroughly, and delays making a proper decision or resorts to external consultants for assistance.
Roger Gibson
Spring 2014
I am indebted to my family and Dayna for their encouragement and support during the writing of this book. Thanks are also due to my past and present colleagues who have offered numerous helpful suggestions.
Finally, the views expressed in this work are my own and I take full responsibility for them.
This book is a practical text that seeks to demystify the measurement of site labour/resource productivity.
In line with the Society of Construction Law Delay and Disruption Protocol launched in October 2002, this book also puts forward a rational and sufficiently accurate method of quantifying the effects of disruption in terms of both cost and time.
Disruption claims impact on the whole of the construction industry, so this book is written for all those members of the construction industry who are involved in submitting, evaluating, awarding, managing and resolving disruption claims.
It is my view that the methods used to quantify disruption must be readily usable by site management. Agreement at this level is the target of the solutions proposed, as it is hoped that this prevents the claim escalating to the formal dispute resolution procedures. It has been my experience that resolving claims for delay and disruption at site level reduces the souring of site relationships and prevents loss of senior management/head office time, which in turn prevents the cost of formal dispute resolution (adjudication, arbitration and litigation).
Lesen Sie weiter in der vollständigen Ausgabe!
Lesen Sie weiter in der vollständigen Ausgabe!
Lesen Sie weiter in der vollständigen Ausgabe!
Lesen Sie weiter in der vollständigen Ausgabe!
Lesen Sie weiter in der vollständigen Ausgabe!
Lesen Sie weiter in der vollständigen Ausgabe!
Lesen Sie weiter in der vollständigen Ausgabe!
Lesen Sie weiter in der vollständigen Ausgabe!
Lesen Sie weiter in der vollständigen Ausgabe!
Lesen Sie weiter in der vollständigen Ausgabe!
Lesen Sie weiter in der vollständigen Ausgabe!